Case Study

Party Wall Dispute Resolution CityLabs London

The Project

Earl Kendrick were appointed to assist in resolving a dispute between two commercial owners regarding the demolition and rebuilding of a deteriorated party fence wall where both tree roots and Japanese knotweed were alleged to have contributed to the instability. 

2

commercial properties

1

party fence wall in severe disrepair

2

contributing causes

Our Goals

Objectives

To identify the true causes of the wall’s deterioration, determine each party’s degree of responsibility, ensure statutory compliance under the Party Wall etc. Act 1996, and support both owners in reaching a fair cost allocation while preserving their commercial relationship. 

Outcomes

Following joint inspections, expert analysis, and structured negotiation, the parties agreed a cost-sharing arrangement reflecting both the adjoining owner’s tree impact and the building owner’s knotweed presence. This avoided escalation to litigation, provided clarity on liability, and enabled the safe reconstruction of the wall with full documentation and mutual agreement. 

Location

CityLabs, London

Scope

Ensure statutory compliance under the Party Wall etc. Act 1996,

EK services provided

“Earl Kendrick identified the causes of wall deterioration, determined party responsibilities under the Party Wall Act 1996, and facilitated a fair cost allocation while preserving the commercial relationship between both owners.”
1 / 2

Our Approach

We coordinated a joint inspection, obtained specialist advice on structural impact, reviewed statutory obligations, and guided both surveyors through a balanced evidence-based negotiation. Each contributing factor was assessed on merit, enabling discussions to centre on responsibility rather than accusation. This approach created a path to agreement without damaging the long-term working relationship between the two commercial owners. 

The Result

The dispute concluded with a practical and equitable solution grounded in technical evidence. A cost-sharing agreement allowed the wall to be demolished and rebuilt safely, and the documented findings clarified the roles of both the tree roots and knotweed in the deterioration. The process remained transparent and proportionate, preventing unnecessary legal escalation and enabling the owners to progress with essential structural works. 

Contact us

FAQs

The wall’s failure had more than one contributing factor, which meant neither owner held sole responsibility. The building owner attributed the damage to the adjoining owner’s tree, while the adjoining owner’s surveyor identified Japanese knotweed originating from the opposite side. When multiple causes overlap, the challenge is determining the extent to which each side contributed. This requires careful investigation, expert input, and negotiation to reach a fair proportion of responsibility. 

Both surveyors carried out a joint inspection and gathered specialist input on how tree roots and knotweed behave structurally. Tree roots can undermine foundations and push masonry out of alignment, while knotweed can penetrate cracks and accelerate deterioration. By comparing visible damage patterns with expert advice, the surveyors identified how each factor influenced the wall’s instability and used that evidence to guide discussions on cost-sharing and responsibility. 

The Act provides a framework for notifying works, recording conditions, and agreeing responsibilities for shared structures. It does not automatically assign fault but ensures a transparent process where each owner’s rights are respected. The surveyors applied the Act to manage access, agree the method of demolition and rebuilding, and document findings. This structure reduced the risk of contentious claims by keeping discussions evidence-based and proportionate. 

They gathered evidence on the presence and impact of knotweed, obtained expert advice, and demonstrated how it contributed to the wall’s condition. They balanced firm advocacy with a fair approach, ensuring the final agreement reflected both sides’ involvement. Their role included explaining the legal position, negotiating constructively, and helping prevent unnecessary legal escalation by focusing on a solution that was technically justified and mutually acceptable. 

Avoiding court saved both owners significant time, cost, and disruption. The technical issues were resolved more efficiently through expert discussion, and the relationship between the neighbouring commercial properties was preserved. A negotiated agreement also offered more flexibility than a court judgment, allowing the parties to tailor cost-sharing to their specific circumstances. Ultimately, both owners gained certainty, avoided reputational strain, and progressed with rebuilding the wall in a controlled, cooperative way. 

 

Contact our Director

Abbie Reid
Head of Party Wall Surveying

e: abbie.reid@earlkendrick.com

Contact one of our experts today

Questions about a building, project or survey? Get in touch and our team is ready to help with practical straight talking advice

Contact us

What we do

Sectors

About Us

Case Studies

Learn With Us

News & Views

1. London Office

Earl Kendrick
The Building Centre
26 Store Street
London
WC1E 7BT

2. North Office

Earl Kendrick
Parsonage Chambers
3 Parsonage
Manchester
M3 2HW

4. Midlands Office

Earl Kendrick
Edmund House,
12-22 Newhall Street
Birmingham
B3 3AS

4. South Coast Office

Earl Kendrick
Foundry Hove
3 Ellen St
Brighton and Hove
Hove
BN3 3LN

4. West Office Bristol

Earl Kendrick
Bristol Castle Park
All Saints' Street
Bristol
BS1 2LZ

5. West Office Cardiff

Capital Tower
Greyfriars Road
Cardiff
Wales
CF10 3AG

T: 0203 6671510

6. West Office Exeter

Earl Kendrick Associates (West)
The Mount
72 Paris St
Exeter
EX1 2JY

6. West Office Torquay

Earl Kendrick
Suite 41
15 Montpellier Road
Torquay
TQ1 1DL

T: 0203 6671510

Copyright © 2025 Earl Kendrick Limited. All rights reserved. Registered in England & Wales No. 07474203 | VAT Registration No. 108635810Registered Office: 2nd Floor, One Hobbs House, Harrovian Business Village, Bessborough Road, Harrow HA1 3EXHosted and Built by NXRD

Privacy Preference Center